log [2020/06/03 13:14] – [12th Week Report] team2log [2021/03/23 11:14] (current) – external edit 127.0.0.1
Line 50: Line 50:
  
 ==== 15th Week Report ====  ==== 15th Week Report ==== 
 +During this week, the team finished the Overleaf paper and send it to the ICL2020 juri. The problems regarding CopeliaSim were fixed and now just need to change some minor details. Also the video and the manual are almost complete and will be uploaded to the deliverables on the begining of the next week. For the next week the team will focus on finishing the deliverables and start preparing the final presentation.
 ==== 16th Week Report ====  ==== 16th Week Report ==== 
 +This was the final week of the EPS project. During the week the team had to finish the things that were missing, such as the video, the manual and the wiki report. Now the focus is to prepare the final presentation, that will take place on the next week.
  
-==== 17th Week Report ====  
  
  
Line 219: Line 219:
  
 === Agenda: === === Agenda: ===
 +  * Manual 
 +  * Video 
 +  * Simulation
 ==== 16th Meeting (2020-06-09) ==== ==== 16th Meeting (2020-06-09) ====
  
 === Agenda: === === Agenda: ===
  
 +  * Previous week: Manual, video, simulation, poster
 +  * Upcoming week: Simulation, report, manual
 ==== 17th Meeting (2020-06-16) ==== ==== 17th Meeting (2020-06-16) ====
  
 === Agenda: === === Agenda: ===
  
-==== 18th Meeting (2020-06-23) ==== +  *Final Presentation
- +
-=== Agenda: ===+
  
  